The Mumbai Metro Rail Corporation (MMRC) achieved a major milestone as the trial train for Aqua Line Phase 2B reached Cuffe Parade, completing its 10.99 km journey from Acharya Atre Chowk. This marks a key step toward full commissioning, reinforcing MMRC’s commitment to world-class urban transit for Mumbai commuters.
Mumbai Metro Aqua Line Phase 2B Trial Train Successfully Reaches Cuffe Parade:
This development is a significant step towards the commissioning of Aqua Line Phase 2B, showcasing progress in rolling stock integration, track infrastructure, and civil works. MMRC is now focusing on the completion of system fitments, architectural finishes, and road restoration to ensure full operational readiness.
The 33.5 km Mumbai Metro Aqua Line is progressing in phases:
- A 12.69 km stretch from Aarey JVLR to Bandra Kurla Complex (BKC) has been operational since October 7, 2024.
- System trials for Phase 2A (Dharavi to Acharya Atre Chowk) covering 9.77 km, including seven stations, have already commenced.
- The latest milestone in Phase 2B, from Acharya Atre Chowk to Cuffe Parade, is crucial for final integration and commissioning.
With Overhead Catenary System (OCS) and track installation completed, MMRC is entering the final phase, ensuring Mumbai’s underground metro revolution is ready for commuters soon.
Insights:
MMRC Managing Director, Ms. Ashwini Bhide stated, “Today is a crucial day for us as we move closer to completing another challenging milestone. Train trials for Phase 2A from Dharavi to Acharya Atrey Chowk are in full swing, and simultaneously, we have successfully initiated train movement from Acharya Atrey Chowk to Cuffe Parade. We are committed to commissioning the entire Line by July 2025.”
Director Projects, Mr. S. K. Gupta said, ”MMRC continues to work diligently toward the overall completion of balance works to ensure a seamless and efficient metro service for Mumbai’s commuters. The successful train trials reaffirm the project’s progress, bringing the city one step closer to a world-class urban transit system”.
Conclusion:
The trial train’s arrival at Cuffe Parade marks a defining moment for Mumbai’s metro expansion. With critical infrastructure in place and final preparations underway, the Aqua Line’s full commissioning is within reach. MMRC remains committed to delivering a world-class, efficient, and seamless transit system for Mumbaikars.
Source: MMRC – Press Release | Images Credit: Mumbai Metro 3