Mumbai-Ahmedabad Bullet Train update: 260m PSC bridge cast near Kosamba, Surat

The Mumbai-Ahmedabad Bullet Train project achieved another milestone with the completion of its 5th Pre-stressed Concrete (PSC) bridge. Spanning 260 meters over National Expressway-4 near Kosamba, Gujarat, the bridge was constructed using the Balanced Cantilever Method. This vital infrastructure links Surat and Bharuch stations, ensuring seamless connectivity along the high-speed corridor.


Introduction:

The bridge, which crosses the under-construction National Expressway-4 that connects Delhi and Mumbai via Rajasthan and Gujarat, plays a crucial role in the high-speed rail alignment. It is strategically positioned between Surat and Bharuch Bullet Train stations, contributing to uninterrupted high-speed rail operations in the future.

Innovative Construction Approach:

  • The bridge features a total of 104 precast segments and consists of four spans configured as 50m + 80m + 80m + 50m.
  • Built using the Balanced Cantilever Method, this technique is particularly suited for larger spans, offering structural efficiency and stability.
  • Given its location over a busy expressway, the construction was meticulously planned to ensure the highest safety standards for both workers and vehicular traffic.
  • The project team implemented strategic measures to minimize disruptions while maintaining smooth traffic flow.

Strengthening High-Speed Rail Connectivity:

With the completion of this bridge, the Mumbai-Ahmedabad Bullet Train project continues to make steady progress. The new infrastructure enhances connectivity between key stations and strengthens India’s ambition of creating a world-class high-speed rail network.

Details of completed PSC bridges in Gujarat:

S.No. Length of bridge (in m) Span Configuration Bullet Train Stations District Location Completed on
5th PSC Bridge 260 Four spans of configuration 50m + 80m + 80m + 50m Between Surat & Bharuch Surat National Expressway – 4 22 Feb 2025
4th PSC Bridge 210 Four spans of configuration 40m + 65m + 65m + 40m Between Anand & Ahmedabad Kheda NH-48 09 Jan 2025
3rd PSC Bridge 210 Four spans of configuration 40m + 65m + 65m + 40m Between Vapi & Bilimora Valsad NH-48 02 Jan 2025
2nd PSC Bridge 210 Four spans of configuration 40m + 65m + 65m + 40m Between Surat & Bilimora Navsari NH-48 01 Oct 2024
1st PSC Bridge 260 Four spans of configuration 50m + 80m + 80m + 50m Between Surat & Bilimora Navsari NH-48 18 Aug 2024

Inspection:

Shri Ravneet Singh Bittu, Minister of State for Railways and Food Processing Industries, visited the Ahmedabad Bullet Train station site to assess the ongoing construction progress. During his visit, he reviewed the project’s developments and engaged with engineers and workers, acknowledging their efforts in advancing India’s high-speed rail infrastructure.

Conclusion:

The successful completion of the 5th PSC bridge marks a significant step forward in the Mumbai-Ahmedabad Bullet Train project. As construction progresses, such engineering feats highlight India’s commitment to advanced rail infrastructure, ensuring efficient and safe connectivity while integrating seamlessly with national expressway networks.


Source: NHSRCL – Press Release | Image Credit: NHSRCL