The Mumbai-Ahmedabad Bullet Train project achieved another milestone with the completion of its 5th Pre-stressed Concrete (PSC) bridge. Spanning 260 meters over National Expressway-4 near Kosamba, Gujarat, the bridge was constructed using the Balanced Cantilever Method. This vital infrastructure links Surat and Bharuch stations, ensuring seamless connectivity along the high-speed corridor.
Introduction:
The bridge, which crosses the under-construction National Expressway-4 that connects Delhi and Mumbai via Rajasthan and Gujarat, plays a crucial role in the high-speed rail alignment. It is strategically positioned between Surat and Bharuch Bullet Train stations, contributing to uninterrupted high-speed rail operations in the future.
Innovative Construction Approach:
- The bridge features a total of 104 precast segments and consists of four spans configured as 50m + 80m + 80m + 50m.
- Built using the Balanced Cantilever Method, this technique is particularly suited for larger spans, offering structural efficiency and stability.
- Given its location over a busy expressway, the construction was meticulously planned to ensure the highest safety standards for both workers and vehicular traffic.
- The project team implemented strategic measures to minimize disruptions while maintaining smooth traffic flow.
Strengthening High-Speed Rail Connectivity:
With the completion of this bridge, the Mumbai-Ahmedabad Bullet Train project continues to make steady progress. The new infrastructure enhances connectivity between key stations and strengthens India’s ambition of creating a world-class high-speed rail network.
Details of completed PSC bridges in Gujarat:
S.No. | Length of bridge (in m) | Span Configuration | Bullet Train Stations | District | Location | Completed on |
5th PSC Bridge | 260 | Four spans of configuration 50m + 80m + 80m + 50m | Between Surat & Bharuch | Surat | National Expressway – 4 | 22 Feb 2025 |
4th PSC Bridge | 210 | Four spans of configuration 40m + 65m + 65m + 40m | Between Anand & Ahmedabad | Kheda | NH-48 | 09 Jan 2025 |
3rd PSC Bridge | 210 | Four spans of configuration 40m + 65m + 65m + 40m | Between Vapi & Bilimora | Valsad | NH-48 | 02 Jan 2025 |
2nd PSC Bridge | 210 | Four spans of configuration 40m + 65m + 65m + 40m | Between Surat & Bilimora | Navsari | NH-48 | 01 Oct 2024 |
1st PSC Bridge | 260 | Four spans of configuration 50m + 80m + 80m + 50m | Between Surat & Bilimora | Navsari | NH-48 | 18 Aug 2024 |
Inspection:
Shri Ravneet Singh Bittu, Minister of State for Railways and Food Processing Industries, visited the Ahmedabad Bullet Train station site to assess the ongoing construction progress. During his visit, he reviewed the project’s developments and engaged with engineers and workers, acknowledging their efforts in advancing India’s high-speed rail infrastructure.
Conclusion:
The successful completion of the 5th PSC bridge marks a significant step forward in the Mumbai-Ahmedabad Bullet Train project. As construction progresses, such engineering feats highlight India’s commitment to advanced rail infrastructure, ensuring efficient and safe connectivity while integrating seamlessly with national expressway networks.
Source: NHSRCL – Press Release | Image Credit: NHSRCL