Madhya Pradesh Metro Rail Corporation’s MD, Shri S. Krishna Chaitanya, IAS, inspected construction progress between Subhash Nagar and AIIMS Stations, including the Subhash Nagar Depot. Meanwhile, rapid advancements in Karond Chauraha Metro construction under Package-BH03 include ongoing pile foundation works, showcasing steady progress on Bhopal Metro’s Priority Corridor development.
Key Highlights:
- Subhash Nagar to AIIMS Station Inspection: Shri Chaitanya reviewed ongoing construction between Subhash Nagar and AIIMS Stations. He evaluated the progress and ensured work aligned with project timelines.
- Subhash Nagar Depot Updates: The MD also visited the Subhash Nagar Depot, a critical facility for metro operations. He examined construction quality and provided guidance for future activities.
- Karond Chauraha Metro Development: Under Package-BH03, construction at Karond Chauraha is progressing swiftly. Pile foundation work, an essential phase, is underway, marking rapid advancements in the project.
MD’s Remarks:
During the site visits, Shri Chaitanya emphasized the importance of maintaining safety and quality standards while adhering to the project schedule. He expressed satisfaction with the progress and encouraged the team to continue its momentum.
Conclusion:
The Bhopal Metro Priority Corridor continues to progress steadily, with significant milestones achieved in both station and depot construction. Shri S. Krishna Chaitanya’s site inspection highlights the project’s commitment to timely execution and quality. With swift advancements at Karond Chauraha, the metro system edges closer to transforming urban mobility in Bhopal.