Pune Metro Update: 3rd Span of Pune Metro at Anand Nagar Completed

Pune Metro Update: 3rd Span of Pune Metro at Anand Nagar Completed

Want create site? With Free visual composer you can do it easy.

Date of Post: 21 July, 2018

Pune: 3rd span of Pune Metro at Anand Nagar completed. Despite of continuous rains, pier formation work for viaduct of Reach-2 Vanaz-Civil Court is in progress. Soon a launching girder will be installed to speed up the work.

Recent Progress in Pune Metro-

19 July 2018: work has started at Bhosari near Nashik Phata for Reach-1 PCMC-Range Hills. Piling operation started using a “Piling Rig” for piles to be inserted to support the formation of pillar foundation.

16 July 2018: Update of riverbed Reach-2 civil work- 102 pilling completed with the help of pilling rig ; Footing for 24 piers completed ; 23 piers ready till ground level, 3 piers ready till pier cap

13 July 2018: Formation of 15th span is in progress at Kharalwadi for Reach 1 PCMC-Range Hills viaduct. Total 142 segments are erected. 107 piers and 50 pier caps are completed.

05 July 2018: Updates from casting yard near Wakad- 170 viaduct segments are ready & stacked for Pune Metro Reach-2 Vanaz-Civil Court. 20 segments are already launched at Anand Nagar.

04 Jul 2018: Total 20 segments are launched for the formation of viaduct Pune Metro Reach-2 Vanaz-Civil Court, 18 pillars with 7 pier caps are completed.


Source: Pune Metro