Nagpur: The second inspection of the at grade stretch of Nagpur Metro would be held in February by the Commissioner of Metro Rail Safety (CMRS).

Brief On The Inspection

  • The first inspection was held on January 16
  • There is a gap of 20 days between the two inspections customarily.
  • The commercial operations of this section will start in February end or March depending on the time taken by the CMRS to issue the final certificate.
  • On Tuesday, Jain accompanied by deputy commissioners of railway safety (DCRS) GP Garg and Uttam Prakash had inspected the at grade stretch of Nagpur Metro.
  • They also had reviewed the Mihan train maintenance depot.
  • The team of CMRS had inspected passenger facilities and other operation rooms at the station.

The First Inspection

  • Source said, during the first inspection, Arvind Kumar Jain, CMRS, central circle, Mumbai, had inspected
  • The Brake System
  • Evacuation System
  • On Board Safety Measures For Passengers
  • Passenger Facilities
  • Machines like hydraulic jack and shunter, emergency rescue equipment etc.

The Second Inspection

  • The CMRS will test the track and stations, during the second inspection.
  • “If Jain is satisfied with our equipment and facilities he will issue a certificate within some days. Else he may ask us to take action on some fronts,” the source further said.

Image Credit: Nagpur Metro