Nagpur Metro Update: Mahametro To Complete Work On Hingna depot to Subhash Nagar Stretch Of Nagpur Metro Project By August

Nagpur Metro Update: Mahametro To Complete Work On Hingna depot to Subhash Nagar Stretch Of Nagpur Metro Project By August

Want create site? With Free visual composer you can do it easy.

Date Of Post: 30 Jan, 2018

Nagpur: Mahametro has set a target of completing Hingna depot to Subhash Nagar stretch by August this year. The construction work of the viaduct from Hingna depot to Subhash Nagar is 50 percent complete, a Mahametro official.

More Information:

  • He said,”The civil work will be completed by June end. Laying of tracks and erection of electric poles would be done along with viaduct construction. These two works plus installation of signalling and telecommunication systems will be over by August. The five stations on the section — Lokmanya Nagar, Bansi Nagar, Wasudeo Nagar, Rachana T-point and Subhash Nagar — will become functional by then. Finishing would, however, go on for some more months.”
  • After this elevated section is ready, Mahametro will conduct a trial run on this section and then invite RDSO (Research Design & Standards Organization) for inspection.
  • This will be followed by a visit of CMRS (Commissioner of Metro Rail Safety) and then commercial operations will commence.

    Image Credit: Nagpur Metro