Mumbai: MMRC (Mumbai Metro Rail Corporation Limited), On Wednesday, signed first System Contract Agreement for the Electrical System works of 25 kV Traction System for Colaba-Bandra-Seepz Metro-3 project with “Consortium of Alstom Transport India Ltd & Alstom Transport S.A”, a release in MMRC said. The Contract Agreement was signed by Mr. A.A.Bhatt, Director (Systems) on the behalf of MMRC and by Mr. Sriram Raju & Mr. Bruno Izambart on behalf of Alstom Consortium, it said.

Image Credit: Mumbai Metro 3

More Information:

  • This package mainly covers design, installation & commissioning of Rigid Overhead Contact System and Auxiliary substations.
  • Letter of Award (LoA) for this work was issued earlier on 21 February 2018.
  • The release said, the work consists of laying Overhead Rigid conductor system in Underground tunnel alignment of 33.5 km route length, flexible & retractable type OCS in Depot, laying of 33kV & 25kV cable, Auxiliary Substation at 27 stations and other associated works etc.

Image Credit: Mumbai Metro 3

  • 25kV Traction works is a critical component of Metro 3 implementation, Managing Director MMRC, Ms. Ashwini Bhide said.
  • We aim to implement robust and technologically advanced Traction system for Metro-3 and complete the works in time so that Line -3 project can be completed in stipulated timelines, Bhide said.