IRCON–DRA JV has successfully completed viaduct work at three major level crossings in Ahmedabad—Punit Nagar, Maninagar, and Vatva—despite urban challenges. Progress includes seven viaduct crossings, two flyovers, a road underpass, and a canal crossing. This marks significant advancement in India’s ambitious Bullet Train Project (Package C7).
Major Achievements:
- Completion of three viaducts in Ahmedabad amidst Indian Railway tracks and busy city roads.
- Construction of seven viaduct crossings out of the project’s planned 31 crossings.
- Completion of two major flyovers: Guruji Flyover and Vatva Narol Flyover.
- Successful development of a road underpass and a crossing over Ghodasar Canal.
Challenges Overcome:
Building in Ahmedabad’s densely populated areas posed unique hurdles, with Indian Railway tracks on one side and urban structures on the other. Despite these difficulties, the JV maintained its pace and ensured quality construction.
Significance:
These milestones highlight the commitment of IRCON-DRA JV to deliver world-class infrastructure under tight timelines, paving the way for India’s first Bullet Train to revolutionise connectivity.
Conclusion:
The completion of critical viaduct and flyover works underscores IRCON-DRA JV’s dedication to overcoming complex challenges and driving progress on the Bullet Train Project. This achievement reinforces India’s commitment to modernising its rail infrastructure and bringing the nation closer to its high-speed rail aspirations.
Source: IRCON | Images Credit: IRCON