IRCON has advanced Mission 100% Electrification by completing the 132/25 kV Golakganj Traction Substation in North Frontier Railways’ Alipurduar Division and commissioning a 9-km 132 kV transmission line in Tripura. These projects enhance eco-friendly train operations, enabling 25kV electric traction while reducing carbon emissions and supporting sustainable railway infrastructure.
Project Highlights:
Golakganj Traction Substation Completion:
- Commissioned the 132/25 kV Golakganj Traction Substation in the Alipurduar Division.
- Facilitates operations of trains on 25kV electric traction.
- Contributes to reduced carbon emissions and improved operational efficiency.
Udaipur Traction Substation Transmission Line:
- Completed a 9-km 132 kV transmission line from Udaipur 132kV Grid Substation to 132/25 kV Udaipur Traction Substation.
- Supports train operations on the Agartala-Sabroom section in Tripura.
Impact on Railways:
- These developments are pivotal in achieving IRCON’s goal of sustainable, electrified railway infrastructure.
- Enhanced efficiency and sustainability align with India’s commitment to eco-friendly transportation.
Conclusion:
These achievements mark a significant stride in India’s railway modernization efforts. By facilitating 25kV electric traction and reducing carbon emissions, IRCON continues to spearhead sustainable infrastructure development, bringing the Indian Railways closer to achieving Mission 100% Electrification and fostering a greener future for rail transport.