Chennai: CMRL (Chennai Metro Rail Limited) completed building of one of the two tunnels in Anna Salai.

The tunnel will connect May Day Park to AG-DMS covering a distance of 3.7 kilom.

Image Credit

The line is expected to get operational by December 2018.

More Information:

  • The giant TBM (Tunnel Boring Machine) broke the fibre reinforced concrete wall & entered AG-DMS station on Wednesday, signalling completion of one of the two tunnels, metro officials said.
  • An official said,”We now have the other tunnel to complete which is about 450m away from achieving break through. We will complete it by next month.”
  • Officials said, once the tunnelling under Anna Salai is complete, traffic will be restored to its original by December end after removing the TBM from the site & closing the shafts cut to build the stations.