70% Of The Civil Work Of The Cantilever Span (Metro Bridge) Over River Gomti Completed By LMRC

70% Of The Civil Work Of The Cantilever Span (Metro Bridge) Over River Gomti Completed By LMRC

Want create site? With Free visual composer you can do it easy.

Date Of Post: 09 June, 2018

Approximately 70% of the Civil Work of the Balanced Cantilever Span (Metro Bridge) being constructed by Lucknow Metro Rail Corporation over River Gomti near Hanuman Setu as well as completed by the Metro Engineers which was reviewed today by Shri. Kumar Keshav, Managing Director, Lucknow Metro Rail Corporation  who also saw the construction work of Viaduct/Pillars at Netaji Subhash Park’ where a pre-casted ‘Span’ of 45 Meter has been erected, which has been merged from one side with the elevated section of this corridor via the balanced Cantilever Span of 175 Meters over the Gomti River.

After this, the Managing Director saw the ongoing construction work of ‘Vishwavidyalaya Metro Station’ and asked the contractor M/s L&T to speed up the work which are taking place in this section along with this, he also saw the construction work which are taking place at the IT College.

 Shri. Kumar Keshav, also visited the Badshah Nagar, Lekhraj, Indra Nagar Metro Station where he was given information about the works which are taking place for the construction of concourse area. Here, the construction work of the entrance gates on both sides is being expedited.

In this corridor, there are some major pillars and sharp curves which were constructed by Lucknow Metro in a smooth manner, these are as:

Pillars HEIGHT OF METRO PILLARS  LOCATION
17.50 Meters Nishatganj
22.50 Meters Kukrail Nala
18.50 Meters Polytechnic Flyover
Curves 193.60 Meters KD Singh Stadium MetroStation
202.60 Meters Government Polytechnic Flyover
128.50 Meters I.T Crossing
852.30 Meters Karamat Crossing
702.3 Meters Kukrail Canal