Mumbai Metro Line 3 is advancing rapidly, with Phase 2 (BKC to Cuffe Parade) reaching 93.6% completion. Rail grinding has been successfully completed on both upline and downline tracks to Cuffe Parade. With Phase 1 fully operational, MMRC is pushing towards the final stages, achieving 95% progress for the overall project.
Mumbai Metro Line 3: Phase 2 on Track for Completion:
With the successful launch of Phase 1 (Aarey to BKC), MMRC is now in the final stages of executing Phase 2, which has reached 93.6% completion. The overall project stands at 94.7% completion, marking a significant leap towards the metro line’s full operation.
Phase-Wise Progress Updates (As of 28-Feb-2025):
- Overall Project Completion: 94.7%
- Civil Works: 99.77%
- Systems Works: 87.7%
- Tunneling: 100%
- Station Construction: 99.22%
- Depot Civil Works: 100%
- Mainline Track Works: 100%
Phase 2 (BKC to Cuffe Parade) Progress:
- Overall Progress: 93.6%
- Station & Tunnel Works: 99.2%
- Station Construction: 98.4%
- Mainline Track Works: 100%
- Systems Works: 78%
- Overhead Catenary System (OCS) Works: 59.6%
Phase 1 (Aarey to BKC) Progress:
- Overall Progress: 100% (Operational)
- Station & Tunnel Works: 100%
- Mainline Track Works: 100%
- Systems Works: 99.22%
- OCS Works: 100%
Phase 2A (Dharavi to AA Chowk):
- Station Works: 99.03%
- Systems Works: 87%
Phase 2B (Science Museum to Cuffe Parade):
- Station Works: 97.98%
- Systems Works: 73.2%
Conclusion:
With Phase 2 of Mumbai Metro Line 3 reaching its final stages, the city is set to witness a major boost in its metro network. The rapid progress in track laying, station construction, and system works highlights MMRC’s commitment to operationalizing the full corridor soon, enhancing Mumbai’s urban mobility landscape.
Source: Mumbai Metro 3 | Images Credit: Mumbai Metro 3